| Activity |
Time |
| President Appoints Leadership Team |
January 2007 |
| Leadership Team Appoints Quality Improvement
Committee
|
February 2007 |
| Stakeholders Identified |
April 2007 |
| Contact and Input Efforts
|
April 2007 - November 2007 |
| Process of Information for Topic
|
April 2007 - January 2008 |
| SACS-COC Reaffirmation Orientation - Leadership Team |
January 2008 |
| Abstracts for Top-Ideas submitted for comment
Team - First Narrative Draft Complete |
January 2008 |
| Stakeholder Vote - Narrow to Three Ideas
|
February 2008 |
| Feasibility Study of Top Three Ideas |
February 2008 - March 2008 |
| Quality Improvement Committee submits QEP Topic to Leadership Team |
April 2008 |
| Leadership Team Appoints Quality Action Committee |
August 2008 |
| Writing of the QEP Proposal Begins |
September 2008 |
| Submit Draft of QEP to Leadership Team |
June 2009 |
| Revisions |
June 2009 - July 2009 |
| Submit Final QEP to Leadership Team |
August 7, 2009 |
| Submission of QEP to on-site Team Members |
August 21, 2009 |